1. Demand a written site logistics plan before contract
A site logistics plan is a scaled site plan showing where each construction resource sits during each phase of the build. It should show the site fence, the crane pad, the material lay-down zone, the site toilet, the skip location, delivery vehicle access route, worker parking, and any temporary hoardings on the street or neighbour boundary.
On a narrow-block build, the plan cannot stay static. Different phases require different arrangements: the slab pour needs a concrete pump position; the framing phase needs timber stack space; the roof phase needs crane access; the cladding phase needs scaffolding. A good plan shows the arrangement for each phase, with dates.
If the builder does not provide a written site logistics plan as part of the contract package, ask for one. This is not an unreasonable request. Any experienced narrow-block builder has plans they can adapt to your site in an afternoon. A builder who cannot or will not produce one is likely to hit logistics problems during the build that the client will end up paying for.