1. Understand the baseline side setback under the Planning and Design Code
The Planning and Design Code Deemed-to-Satisfy provisions set a ground-floor side setback that varies with the zone. In most General Neighbourhood and Suburban Neighbourhood zones the baseline is 900mm from each side boundary for a single-storey wall, increasing to 1200mm or 1500mm for upper storey walls depending on wall height.
These are the numbers that trigger a straightforward Deemed-to-Satisfy assessment. Meet these setbacks with a clean design and your application is typically decided within four to six weeks.
Fall below these numbers, and the application moves to performance assessment. That is where each council applies its own culture and interpretation, and where the timeline stretches out to twelve to twenty weeks.