Planning permit vs building permit explained, when you need one or both, and the Melbourne councils with the slowest queues in 2026.

By George Giannakakis · B.Arch.Studies · M.Arch (UniSA) · RLA300580
Last reviewed: · How we research
Building permit = engineering + safety compliance sign-off. Issued by a private building surveyor or council. Every new dwelling, extension or structural change needs one. Takes 2-6 weeks and rarely refused if design meets the National Construction Code. Planning permit = council approval that a proposed use / design fits their planning scheme. Only some projects need one, but the ones that do stall the whole build until it lands. Check VicPlan before you start any design.
Heritage Overlay lots (any changes visible from the street). Second dwellings / dual occupancy. Any Rescode variation - side setback, front setback, site coverage, garden area, permeability. Development plan overlay lots. Vegetation Protection Overlay / Significant Landscape Overlay. Bushfire Management Overlay upgrades. Any subdivision. Some Neighbourhood Character Overlays.
Yarra: 5-9 months average for straightforward planning permits, 12+ for anything contested. Stonnington: 4-8 months. Bayside: 4-8 months. Boroondara: 4-9 months. Port Phillip: 3-7 months. Melbourne CBD: 3-7 months. Faster councils (typical 2-5 months): Wyndham, Casey, Whittlesea, Melton, Cardinia - the outer growth corridors have faster queues because most estate designs are pre-approved and code-compliant.
After the build is finished, your building surveyor issues an Occupancy Permit certifying the home is code-compliant and safe to move into. This is what gives you the keys. The builder cannot legally hand over without one. Also required by every lender before final progress payment is released.
Usually no. Most estates in Wyndham, Casey, Melton and Whittlesea have pre-approved design controls and code-compliant zoning that allow builders to lodge straight to a private surveyor for a building permit. You only need a planning permit if you request non-standard design elements, are in a Bushfire Management Overlay, or the estate's Section 173 or MCP requires it.
Use VicPlan at mapshare.vic.gov.au - the free official planning-scheme map. Enter your address, tick "Overlays" and it shows heritage overlays, DPOs, VPOs, SLOs, BMOs and all planning zones. Do this BEFORE signing a land or house contract.
Yes - via VCAT (Victorian Civil and Administrative Tribunal). Appeals cost $500-$3,500 in fees plus $8,000-$40,000 in planning + legal consultancy. VCAT hearings currently run 9-18 months in Melbourne. Success rate for reversing a straight-up council refusal sits around 40-60% depending on grounds.
Building in South Australia instead? See the Adelaide version of this guide →
BuildPilot is preparing to open in Victoria. Join the waitlist so we contact you first when the matcher goes live.