KDR on a Melbourne block is only viable outside Heritage Overlays - which cover about 40% of inner + middle-ring blocks. The path takes 16-24 months from decision to keys and needs demolition consent, potential planning permit, then building permit. Here is the honest sequence.
$500K - $1.2M all-in
demolition + rebuild + temp accommodation + services
16 - 24 months
decision to Occupancy Permit

What this means in practice
Non-heritage middle + outer-ring Melbourne blocks
The steps that move the needle. We sit beside you on each one.
Any Heritage Overlay grading usually kills KDR. Confirm before spending on plans.
Melbourne homes pre-1985 almost always contain asbestos. Get a licensed assessor + certified disposal quote.
Standard non-heritage lots need a demolition permit (2-8 weeks). Heritage-adjacent lots also need council planning approval.
Same VBA + DBI checks as any new build. See our new-build journey for the detailed permit path.
2-4 weeks demolition, 12-16 months rebuild. Plan temporary accommodation for the full window.
Adelaide-based advisor. No retainer. No upselling. We have walked this exact journey with hundreds of families.