Knockdown Rebuild Melbourne

Journeys/Melbourne Journey

Knockdown-Rebuild Journey in Melbourne

KDR on a Melbourne block is only viable outside Heritage Overlays - which cover about 40% of inner + middle-ring blocks. The path takes 16-24 months from decision to keys and needs demolition consent, potential planning permit, then building permit. Here is the honest sequence.

Typical cost

$500K - $1.2M all-in

demolition + rebuild + temp accommodation + services

Typical timeline

16 - 24 months

decision to Occupancy Permit

Melbourne knockdown-rebuild in progress on an established block

What this means in practice

Non-heritage middle + outer-ring Melbourne blocks

Get matched with the right builder for your build

A 3-minute questionnaire on budget, block type and build style. We shortlist Adelaide partner builders that fit, and hand you a comparison table. No pushy calls, no commitment.

  • Under 3 minutes. 8 quick questions, no email required to see results.
  • Ranked shortlist. Match score, price band, and where each builder actually builds.
  • Independent. Editorial layer over paid ranking. Builders can't buy their way to the top.

This journey suits you if

  • Non-heritage middle + outer-ring Melbourne blocks
  • 1960s-90s brick veneer past useful life
  • Owners keeping the block 10+ years

What goes wrong most

  • Full block refused by Heritage Overlay (75-85% of HO applications rejected)
  • Asbestos discovery ($5k-$18k extra)
  • Temp accommodation cost during 14-22 month rebuild ($30k-$70k)

How it actually unfolds

The steps that move the needle. We sit beside you on each one.

  1. 1

    Overlay check via VicPlan first

    Any Heritage Overlay grading usually kills KDR. Confirm before spending on plans.

  2. 2

    Asbestos + demolition quote

    Melbourne homes pre-1985 almost always contain asbestos. Get a licensed assessor + certified disposal quote.

  3. 3

    Demolition permit

    Standard non-heritage lots need a demolition permit (2-8 weeks). Heritage-adjacent lots also need council planning approval.

  4. 4

    Select builder + rebuild design + permits

    Same VBA + DBI checks as any new build. See our new-build journey for the detailed permit path.

  5. 5

    Demolish, rebuild, hand over

    2-4 weeks demolition, 12-16 months rebuild. Plan temporary accommodation for the full window.

Find my Melbourne builder

Adelaide-based advisor. No retainer. No upselling. We have walked this exact journey with hundreds of families.