1. Site access decides the cost of everything else
On an established Adelaide block, site access to the rear of the home is often the single biggest cost driver. If the block has a wide side driveway that a bobcat, mini-excavator and concrete truck can reach the rear through, site works run cleanly and the trades can stage materials at the back of the home. If access is through a 900mm side passage between the home and the boundary fence, every cubic metre of concrete, every pallet of bricks and every stick of timber has to be carried by hand.
The impact of poor access is not linear. A hand-barrow site can add 15 to 25 percent to trade labour costs across the whole extension, because every subcontractor charges for the additional time. Some trades will decline the job entirely if access is too tight.
Get a signed site logistics plan from the builder before contract. It should specify the access route for each trade, the location of the site toilet and skip, the delivery windows for major materials, and any temporary fencing or protection of existing garden and paving.